Component Replacement Analysis During Scheduled Dry-Docking
During the scheduled dry-docking, a number of components were replaced due to wear or reaching the end of their service life. These components included:
- Sliding piece
- One sleeve
- O-rings
- Gasket
- Back-up ring
- Oil seal
- Four sliding blocks
- Locking plate
- Rung spacer
- Locking wires
- Spacer ring
- Plugs
- Shim
- Seven sleeves
Visual inspection of the replaced components did not reveal any signs of damage that would suggest an accident. Therefore, we conclude that the replacements were part of routine maintenance and wear-related issues associated with scheduled dry-docking.