How to Shorten a Project Schedule with Extra Resources: The Best Strategy Explained
C-) Crash the project.
Crashing the project involves adding extra resources to critical path activities to reduce their duration and ultimately shorten the project schedule. This is the best option in this scenario since the project network diagram cannot change, and fast tracking may lead to increased risk and rework. Leveling the resources may not have a significant impact on the project schedule, and Monte Carlo analysis is a tool for assessing project risks and uncertainties, not for shortening project schedules.