After completing basement construction, prompt backfilling around the perimeter is crucial. Before commencing backfill, eliminate any accumulated water, loose soil, and construction debris. When employing soil-based backfill materials, prioritize the use of 30% gray soil, optimally-moistened bare soil, or sand soil. It is mandatory to conduct a test fill to verify suitability before proceeding. Strictly avoid substituting construction debris, silt (clay) soil, or cultivated soil for approved materials. Backfill should be evenly distributed, employing a symmetrical approach. Implement layered backfilling with each layer not exceeding 250mm in thickness. After compaction, the backfill soil should achieve a compaction coefficient of ≥0.94. During construction, prioritize avoiding damage to the waterproof layer.

Basement Backfill Best Practices: Ensuring Proper Soil Selection and Compaction