Where a contractorsubcontractor is granted an extension of time is there an automatic right to the recovery of loss and expense answer it more than 200words
When a contractor or subcontractor is granted an extension of time, it does not automatically entitle them to the recovery of loss and expense. The extension of time may simply provide the contractor or subcontractor with additional time to complete the works, without any additional compensation.
In order to recover loss and expense, the contractor or subcontractor must be able to demonstrate that they have incurred additional costs as a result of the delay. This may include, but is not limited to, additional labour costs, material costs, and overheads.
The contractor or subcontractor must also be able to demonstrate that the delay was caused by an event that was beyond their control, such as an act of God, a strike, or a delay caused by the client or their agents. If the delay was caused by the contractor or subcontractor, they will not be entitled to recover any loss and expense.
In addition, the contractor or subcontractor must comply with the relevant contractual provisions regarding the recovery of loss and expense. This may include providing written notice of the delay and the associated costs within a specified timeframe, and providing evidence to support their claim.
It is important to note that the recovery of loss and expense is not automatic, and the contractor or subcontractor must be able to demonstrate that they have incurred additional costs as a result of the delay, and that the delay was caused by an event that was beyond their control. If these conditions are not met, the contractor or subcontractor may not be entitled to recover any loss and expense
原文地址: https://www.cveoy.top/t/topic/flv7 著作权归作者所有。请勿转载和采集!