MRP Worksheet for Product K, A, B, C, and D (8 Weeks)
MRP Worksheet for Product K:
BOM Graph:
- 2 A per K
- 5 B per K
- 1 B per A
- 3 C per A
- 2 D per A
Product K Details:
- Lead Time: 1 week
- On-hand inventory: 0 units
- Lot sizing method: Lot for Lot
Demand:
- Week 4: 100 units
- Week 5: 200 units
- Week 8: 100 units
| Week | Gross Requirements | Scheduled Receipt | Projected On Hand | Net Requirements | Planned Order Receipt | Planned Order Releases | |---|---|---|---|---|---|---| | 4 | 100 | | | 100 | 100 | | | 5 | 200 | 100 | | 100 | 100 | | | 6 | | 200 | | 100 | 100 | | | 7 | | | 100 | | | 100 | | 8 | 100 | 100 | | | | 100 |
MRP Worksheet for Component A:
Component A Details:
- Lead Time: 1 week
- On-hand inventory: 100 units
- Minimum Order: 250 units
- Lot sizing method: Lot for Lot
- Safety Stock: 50 units
| Week | Gross Requirements | Scheduled Receipt | Projected On Hand | Net Requirements | Planned Order Receipt | Planned Order Releases | |---|---|---|---|---|---|---| | 4 | 200 | | 100 | 100 | 250 | | | 5 | 400 | 250 | 100 | 150 | 250 | | | 6 | | 400 | 300 | 100 | 250 | | | 7 | | | 550 | | | | | 8 | 100 | 550 | 800 | | | 250 |
MRP Worksheet for Component B:
Component B Details:
- Lead Time: 1 week
- On-hand inventory: 120 units
- Minimum Order: 600 units
- Lot sizing method: Lot size by 300 units
- Safety Stock: 0 units
| Week | Gross Requirements | Scheduled Receipt | Projected On Hand | Net Requirements | Planned Order Receipt | Planned Order Releases | |---|---|---|---|---|---|---| | 4 | 500 | | 120 | 380 | 600 | | | 5 | 1000 | 600 | 420 | 580 | 900 | | | 6 | | 900 | 720 | 280 | 900 | | | 7 | | | 1020 | | | | | 8 | 500 | 1020 | 720 | | | 500 |
MRP Worksheet for Component C:
Component C Details:
- Lead Time: 1 week
- On-hand inventory: 50 units
- Minimum Order: 800 units
- Lot sizing method: Lot for Lot
- Safety Stock: 50 units
| Week | Gross Requirements | Scheduled Receipt | Projected On Hand | Net Requirements | Planned Order Receipt | Planned Order Releases | |---|---|---|---|---|---|---| | 4 | 300 | | 50 | 250 | 800 | | | 5 | 750 | 800 | 50 | 700 | 800 | | | 6 | | 750 | 50 | 700 | 800 | | | 7 | | | 750 | | | | | 8 | 150 | 750 | 1000 | | | 150 |
MRP Worksheet for Component D:
Component D Details:
- Lead Time: 1 week
- On-hand inventory: 100 units
- Minimum Order: 400 units
- Lot sizing method: Lot size by 400 units
- Safety Stock: 0 units
| Week | Gross Requirements | Scheduled Receipt | Projected On Hand | Net Requirements | Planned Order Receipt | Planned Order Releases | |---|---|---|---|---|---|---| | 4 | 200 | | 100 | 100 | 400 | | | 5 | 400 | 400 | 100 | 300 | 400 | | | 6 | | 400 | 100 | 300 | 400 | | | 7 | | | 400 | | | | | 8 | 200 | 400 | 600 | | | 200 |